The Sanborn County Commissioners and Zoning Board met in a special informational meeting with a representative of a Pipestone, Minn., wind energy company Tuesday morning to discuss a proposed wind farm to be built south of Letcher.
Corey Juhl of Juhl Energy addressed the boards Tuesday morning, calling the project a series of “community wind farms” of just nine to 15 towers. Juhl Energy built the wind farm north of Kimball in Brule County and currently has a project approved near White Lake in Aurora County.
The proposed Sanborn County farm would be located south of Letcher. Juhl says the company is still in discussion with the landowners. The total area of the farm would be between one and one and a quarter sections.
Juhl said that the turbines in this particular site would be no closer than 1,500 feet from the nearest dwelling.
The three sites along the I90 corridor would be linked in order to increase buying power with the energy companies. The Letcher site would use the same NorthWestern Energy line currently running from Letcher by Loomis and towards Mitchell.
Davison County recently denied Juhl Energy’s permit to build the farm there. Juhl says he is unsure what their reasoning was and that their company had never been denied a permit until then.
Brian McGinnis of the Planning and Development District III was available via conference call for the meeting. He helped lay out the process for such a project and options for ordinances that may be put in place and guidelines to follow. He stated that there are several ordinances available from which to model a local one.
“I will make sure the county is protected,” McGinnis said, when concerns of road maintenance and costs to the county were raised.
Juhl said there would be no costs to the county, save some extra time administratively. He stated that Juhl Energy would agree to any regulations the county sees fit and be 100 percent responsible for any costs associated with the farm, including road usage and repairs.
He added that the company hopes to hire graduates from Mitchell Technical Institute for the project that, paperwork and weather permitting, they are hoping to begin construction on this summer. Nine of the 446-foot towers can be built within three months.
Following Tuesday’s informational meeting and after finalizing the contracts with the landowners, the next step is the permitting process and then the commissioners and zoning board can vote to allow or deny the project.
-
Weather
Failure notice from provider:
Connection Error:http_request_failedUpcoming Events
February 2025 SSunday MMonday TTuesday WWednesday TThursday FFriday SSaturday 26January 26, 2025 27January 27, 2025 28January 28, 2025 29January 29, 2025 30January 30, 2025 31January 31, 2025 1February 1, 2025 2February 2, 2025 3February 3, 2025 4February 4, 2025 5February 5, 2025 6February 6, 2025 7February 7, 2025 8February 8, 2025 9February 9, 2025 10February 10, 2025 11February 11, 2025 12February 12, 2025 13February 13, 2025 14February 14, 2025 15February 15, 2025 16February 16, 2025 17February 17, 2025 18February 18, 2025 19February 19, 2025 20February 20, 2025 21February 21, 2025 22February 22, 2025 23February 23, 2025 24February 24, 2025 25February 25, 2025 26February 26, 2025 27February 27, 2025 28February 28, 2025 1March 1, 2025 -
Recent Posts
Contact Us
Archives
Tweet